Jason Lim · Johor Bahru property advisor

Johor’s Future Transport Projects (2026): What Is Built, Approved and Only Proposed

中文 · Bahasa Melayu · Bahasa Indonesia

By Jason Lim, REN 84424 · IQI Realty · Checked on 16 November 2026

Johor’s transport projects are at very different stages. The Gemas–Johor Bahru electrified double track is finished and ETS trains have run to JB Sentral since December 2025. The RTS Link to Singapore is targeted for February 2027. The elevated ART is approved but not built, and the KL–Singapore high-speed rail has no decision.

Quick answer

  • Done: the 192 km Gemas–Johor Bahru electrified double track was launched on 11 December 2025, and ETS trains to JB Sentral started the next day (Malay Mail, 11 December 2025).
  • Next to open: the RTS Link from Bukit Chagar to Woodlands North is targeted for February 2027, subject to safety certification and approvals (LTA and Ministry of Transport, 2 October 2026).
  • Approved, not built: the Cabinet approved the elevated ART (e-ART) at about RM10 billion in May 2026; funding terms were still being negotiated and no routes were published by mid-November 2026.
  • No decision: the KL–Singapore high-speed rail has not been revived; the government will only consider a fully private-funded plan (The Star, 28 February 2026).
  • Roads: two stretches of expressway works near Kulai and on the Senai–Desaru Expressway may open in early 2027 (The Star, 13 November 2026).

Which Johor transport projects are built, approved or only proposed?

Buyers hear about “upcoming” transport at almost every Johor sales gallery. The useful question is which stage each project has reached: operating, under construction (contracts awarded, work on site), approved (government approval or budget, no construction yet) or proposed (no approval to build).

ProjectStage (16 Nov 2026)Official date or latest position
Gemas–JB electrified double track and ETS to JB SentralOperatingLine launched 11 Dec 2025; ETS to JB Sentral from 12 Dec 2025
KTM Shuttle Tebrau (JB Sentral–Woodlands)OperatingEnds six months after the RTS Link starts
KTM Southern Shuttle (Paloh, Kluang, Kulai, Kempas Baru, JB Sentral, Pasir Gudang)OperatingStarted 16 June 2026; extended to Kluang and Paloh from 8 August 2026
RTS Link (Bukit Chagar–Woodlands North)Under construction, in trial runsPassenger service targeted for February 2027
BAS.MY Johor Bahru expansionAnnounced; contract being finalisedFive years from 2027, with 230 new buses
Elevated ART (e-ART)Approved, not builtCabinet approval May 2026; concession not yet signed
North–South Expressway widening (Kulai–Sedenak–Machap)Under construction in phasesPackages due between 2027 and 2028; later phases still seeking approval
Senai–Desaru Expressway upgradingPartly under constructionOne stretch may open Jan–Feb 2027; Phase 2A target Dec 2029
Pasir Gudang Highway upgradingUnder construction3 Dec 2025 to 2 Dec 2028
KL–Singapore high-speed railProposed, no decisionPrivate-sector-only condition; no proposal sent to Singapore
Compiled from the dated official statements and news reports listed under Sources, checked 16 November 2026. Dates are targets set by the authorities and can move.

When will the RTS Link open, and what changes when it does?

The RTS Link is the project closest to opening. On 2 October 2026, Singapore’s Land Transport Authority (LTA) and Malaysia’s Ministry of Transport said passenger service is expected in February 2027. An independent safety assessor must certify the system after trial runs, and both governments must approve the start. The link runs from Bukit Chagar to Woodlands North, on Singapore’s Thomson-East Coast MRT line.

For daily life:

  • Capacity: the system and Bukit Chagar station are designed for 10,000 passengers an hour in each direction (The Star, 28 February 2026).
  • One-stop clearance: Parliament passed a law letting both countries’ immigration checks sit in one building (The Star, 28 February 2026).
  • Fares: to be announced jointly by both governments; not published by 16 November 2026.

The KTM Shuttle Tebrau to Woodlands will stop six months after the RTS Link opens (Bernama, 8 October 2026). Around Bukit Chagar, a bus hub with 20 more bays is planned on Jalan Jim Quee to feed the station. For the detail, see my RTS Link 2026 update, JB homes near the RTS Link station and Woodlands vs Bukit Chagar for commuters.

Is the Gemas–Johor Bahru double track finished?

Yes. The 192 km Gemas–Johor Bahru electrified double-track line was launched on 11 December 2025 at Kempas Baru station, with 11 new stations across Segamat, Kluang, Kulai and Johor Bahru districts (Malay Mail, 11 December 2025). ETS electric trains had already reached Kluang from 30 August 2025 and were extended to JB Sentral from 12 December 2025. The trip from Kuala Lumpur takes about four and a half hours.

It is the one big Johor rail project you can judge on facts rather than plans. Comparing towns along the line? See my Kluang property guide and Segamat property guide.

KTM started the Southern Shuttle commuter service on 16 June 2026, linking Kulai and Kempas Baru with JB Sentral, plus a branch serving Pasir Gudang, and extended it north to Kluang and Paloh from 8 August 2026 (Bernama, August 2026); Budget 2027 promised lower fares (The Star, 8 October 2026). Check the timetable before relying on it daily.

What is the status of the Johor Bahru elevated ART?

The e-ART uses rubber-tyred, tram-like vehicles on an elevated guideway above the roads. Its status, from dated reports:

  • 17 May 2026: the Cabinet approved the project at an estimated RM10 billion (The Star).
  • 2 July 2026: the transport minister told Parliament the federal government will help fund it because private financing alone was not viable, and that terms were still being negotiated (Malay Mail).
  • 9 October 2026: Budget 2027 named the e-ART as the main solution to Johor Bahru’s traffic congestion (Malay Mail).

Not yet known: the final route, stations, opening date and fares. The only published route figures are from a May 2024 state plan with three lines (Iskandar Puteri, Skudai and Tebrau) and 32 stations (Bernama, 14 May 2024); the approved project may differ. The minister has said completion is expected about four years after the letter of acceptance, and I found no report of one being issued by 16 November 2026. My e-ART guide tracks each step.

Before any e-ART runs, expect more buses: the government plans to extend BAS.MY Johor Bahru for five years from 2027 with 230 new buses and new coverage including Terminal Tiram, Johor Jaya, Medini and Universiti Teknologi Malaysia; the minister said in October 2026 that the contract would be finalised soon (Bernama, 8 October 2026). See getting around JB without a car.

Choosing a Johor home around transport?

Tell me where you need to travel (Singapore, JB city, Kulai, KL) and your budget. I'll shortlist homes that work with the roads, trains and buses running today, and show you what is officially confirmed for each area.

WhatsApp Jason

Will the KL–Singapore high-speed rail be revived?

Not yet, and no date exists. The original project was suspended in 2018 and terminated in January 2021, when Malaysia paid Singapore more than RM320 million in connection with the termination (The Edge Malaysia, 7 October 2025). Since then:

  • Malaysia invited private-sector concept proposals in 2023. MyHSR Corporation’s evaluation went to the Cabinet on 8 January 2025, but the outcome was not disclosed (The Edge Malaysia, 7 October 2025).
  • In October 2025 the transport minister said key parameters were being finalised before any request for proposals, with no direct government funding.
  • On 28 February 2026 he said it was premature to discuss it with Singapore, that no proposal had been raised with the Singapore government, and that there had been no major progress (The Star).

Singapore’s transport minister said in July 2024 that Singapore had not received any new proposal from Malaysia (Ministry of Transport Singapore, 2 July 2024). On the record to November 2026, the HSR is a proposal, not a project, and station locations from the cancelled scheme have no standing.

Which new highways and road upgrades are under way in Johor?

The state works and transport committee chairman’s update on road works (The Star, 13 November 2026):

Road projectLengthStage and target
North–South Expressway widening, Senai Utara–Sedenak (Package A)21.8 kmUnder construction since June 2024; target June 2027. The 14.5 km Sedenak–Kulai stretch may open in Feb–Mar 2027
North–South Expressway widening, Kulai–Senai Utara (Package B)Not statedUnder construction since June 2025; target Dec 2027
North–South Expressway, Sedenak–Simpang Renggam (Phase Two)16.6 kmAbout 27% complete; target 27 July 2028
North–South Expressway, Simpang Renggam–Machap (Phase Three)14 kmWork expected to start December 2026; about three years
North–South Expressway, Machap onwards (Phase Four)Not statedProposed; state seeking approval
Senai–Desaru Expressway, Sungai Johor bridge–Sungai Semenchu9.34 kmUnder construction; may open Jan–Feb 2027 (originally April 2027)
Senai–Desaru Expressway, Cahaya Baru–Sungai Johor bridge (Phase 2A)4.7 kmConstruction expected to start late 2026; target Dec 2029
Senai–Desaru Expressway, Sungai Semenchu–Penawar (Phase 2B)10.9 kmProposed; state seeking approval
Source: The Star, 13 November 2026, quoting the Johor state works, transportation, infrastructure and communications committee chairman. Early openings depend on talks with the Malaysian Highway Authority.

Two federal road contracts were awarded in December 2025 (Ministry of Works, 5 January 2026):

  • Pasir Gudang Highway (FT17): 7 km widened from four lanes to six from the Perling interchange to the North–South Expressway slip road at Pasir Gudang, RM174.53 million, 3 December 2025 to 2 December 2028.
  • Sedili Besar, Kota Tinggi: a 3.1 km new road with a 320 m bridge over Sungai Sedili Besar, RM62.11 million, due by 16 December 2028.

Budget 2026 also allocated RM710 million for Johor infrastructure. This included RM325 million for Jalan Parit Panjang from Pekan Ayer Baloi to the Sedenak toll junction, RM60 million for the Taman Muhibbah bypass and RM45 million to replace escalators at JB Sentral and the Causeway checkpoint complex (RTM, 14 October 2025). An allocation is not a finished road. My JB roads and traffic guide covers the main highways in use today.

What are the plans for Senai International Airport?

Senai International Airport, in Kulai district, is Johor’s main airport. The latest dated expansion I could confirm is an RM11.9 million upgrade whose new terminal section opened in August 2023; capacity before it was 4 million passengers a year. The airport operator said then that it aimed to handle 7 million passengers a year by 2030 (Sinar Daily, 5 October 2023). That is the operator’s target, not a government commitment. I found no newer official plan with a construction date, so treat other airport plans as unconfirmed.

For Kulai, Senai and Sedenak, see also Johor data centres and property in Kulai and Sedenak.

How should buyers treat future transport when choosing a home?

I make no claims about what any project will do to prices. What I do with clients:

Foreign buyers: transport plans do not change Johor’s rules. Johor applies an RM1 million minimum for residential property, with only limited exceptions (for example, some serviced apartments sold by developers with state approval); no area is exempt as a whole. See the minimum price guide. For MM2H, I coordinate with a MOTAC-licensed MM2H agent and handle the property side; see MM2H property support.

Where to buy if this matters to you

Compare them on my JB property map, or see Johor’s districts compared.

More Johor living guides: What the RTS Link means for JB property · Live in JB, work in Singapore · Iskandar Malaysia explained · Budget 2027 and JB property

Frequently asked questions

When will the Johor Bahru–Singapore RTS Link open?

Singapore’s LTA and Malaysia’s Ministry of Transport said on 2 October 2026 that RTS Link passenger service is targeted for February 2027. The date depends on trial runs, independent safety certification and approval by both governments. RTS Link fares had not been announced by 16 November 2026.

Can I take the ETS train from Kuala Lumpur to Johor Bahru?

Yes. ETS electric trains have run between KL Sentral and JB Sentral since 12 December 2025, after the 192 km Gemas–Johor Bahru electrified double track was launched on 11 December 2025. The journey takes about four and a half hours, with stops in Segamat, Kluang and Kulai districts.

Is the KL–Singapore high-speed rail going ahead?

No decision had been made on the KL–Singapore high-speed rail by November 2026. In February 2026 Malaysia’s transport minister said it was premature to discuss it with Singapore and that it would only proceed if the private sector funded it fully. The original project was terminated in January 2021.

When will the Johor Bahru elevated ART be built?

The Johor Bahru elevated ART (e-ART) has no opening date. The Cabinet approved it at about RM10 billion in May 2026, and Budget 2027 named it the main fix for JB traffic, but funding terms were still being negotiated in 2026. The minister expects completion about four years after the letter of acceptance is issued.

Which Johor highway stretches may open in 2027?

Two Johor highway stretches may open early in 2027. These are the 14.5 km Sedenak–Kulai stretch of the North–South Expressway widening (February or March 2027) and the 9.34 km Sungai Johor bridge–Sungai Semenchu stretch of the Senai–Desaru Expressway (January or February 2027). The Star reported the state’s update on 13 November 2026.

Should I buy a Johor property because a new transport line is planned nearby?

Buying a Johor property only because a transport line is planned nearby is risky. Projects such as the e-ART and the high-speed rail have no published route or start date. Choose a home that suits your commute today, ask for the dated official source behind any station claim, and treat any future link as a bonus.

Want a Johor home that works with today’s transport?

Tell me where you travel each week, your budget, and condo or landed. I will shortlist homes that work with the roads, trains and buses running now, tell you what is confirmed for each area, and arrange peak-hour viewings so you can test the journey. You can also book an appointment, or a Zoom consultation if you are abroad.

Sources: LTA and Ministry of Transport Malaysia, joint release on the RTS Link service timeline, 2 October 2026; The Star, “On track for the future with RTS, HSR and ECRL”, 28 February 2026; Bernama, on the Southern Shuttle and Shuttle Tebrau, 8 October 2026; Bernama, KTMB extends Shuttle Selatan to Paloh from 8 August 2026, August 2026; Bernama, BAS.MY Johor Bahru to be extended for five years from 2027, 8 October 2026; The Star, “Budget 2027: Good news in store for Southern Shuttle users”, 8 October 2026; Malay Mail, Gemas–JB electrified double-tracking line launched, 11 December 2025; Malay Mail, KL to JB in 4.5 hours on the electric train, 11 December 2025; The Star, Cabinet approves RM10bil E-ART project, 17 May 2026; Malay Mail, Putrajaya to help fund Johor’s RM10b E-ART, 2 July 2026; The Edge Malaysia, JB e-ART terms still under negotiation, July 2026; Malay Mail, Budget 2027: e-ART to be main urban public transport solution in Johor Bahru, 9 October 2026; Bernama, Johor Bahru elevated ART system to have 32 stations, 14 May 2024; The Edge Malaysia, Malaysia yet to decide on development model for KL–Singapore High-Speed Rail, 7 October 2025; Ministry of Transport Singapore, written reply on the prospects of reviving the HSR, 2 July 2024; The Star, “Two highway stretches in Johor may open early”, 13 November 2026; Ministry of Works (KKR), letters of acceptance for high-impact road projects in Johor, published 5 January 2026; Portal Berita RTM, Budget 2026: RM710 million for Johor infrastructure, 14 October 2025; Sinar Daily, Senai airport upgrade and 2030 capacity target, 5 October 2023

Jason Lim, REN 84424, IQI Realty Sdn. Bhd. E (1) 1584/6. General information checked on 16 November 2026 from the dated official statements and news reports listed above; not investment or legal advice. Transport projects can change route, cost or timing, and proposed projects may never be built. Confirm the latest position with the Ministry of Transport, the Ministry of Works, the Malaysian Highway Authority and the Johor state government before relying on it.