By Jason Lim, REN 84424 · IQI Realty · Checked on 15 November 2026
This guide is for condo and serviced residence owners in Johor Bahru, local or foreign, and for tenants who want to change their unit. The short answer: before any renovation you need the management body’s prior written approval under the standard strata by-laws, and the management may ask for a refundable renovation deposit, commonly RM2,000 to RM5,000 or more. Work is limited to the hours in the house rules, debris must leave the building with your contractor, and some changes also need the council’s approval.
Quick answer
- Approval first: standard by-law 27 (Strata Management (Maintenance and Management) Regulations 2015) requires the management’s prior written approval.
- Council too: moving external doors or windows, platforms, safety features, plumbing and full rewiring also need the authority (by-law 28).
- Deposit: commonly RM2,000 to RM5,000 or more, refunded after an inspection (SAYS, May 2026).
- Hours: set by house rules; noisy work usually on weekdays only.
- Fines: additional by-laws can fine an owner, occupant or invitee up to RM200 per breach (Strata Management Act 2013, sections 32 and 70).
- Disputes: management, then the Commissioner of Buildings, then the Strata Management Tribunal (up to RM250,000; RM100 residential fee).
The rules behind condo renovations
Johor strata buildings have three layers of rules. The 30 standard by-laws in the Third Schedule of the 2015 Regulations bind the developer, the joint management body (JMB) or management corporation (MC), and every owner and occupier (Malay Mail, 29 September 2026). Additional by-laws, passed by owners by special resolution under sections 32 and 70 of the Strata Management Act 2013 (Akta Pengurusan Strata 2013, Act 757), can cover floor coverings, refuse and architectural guidelines, and carry fines of up to RM200 per breach. House rules and the renovation form fill in hours, deposits and contractor passes; if a fine rests only on a house rule, ask which by-law supports it (see condo by-laws, access cards and visitors).
| Standard by-law | What it says, in short | What it means for you |
|---|---|---|
| 27: renovation | No renovation without the management’s prior written approval and, where required, the authority’s. The management may ask for a deposit. Work stays inside your parcel and must not weaken any structural part. | Apply before you hire anyone. |
| 28: both approvals | Adding a platform, moving an external door or window, changing a safety feature, moving plumbing or sewerage, or rewiring the whole unit need the authority and the management. Hacking shear walls beyond permitted limits is not allowed. | The council (MBJB, MBIP, MBPG or MPKu) is involved too. |
| 29: outside of the unit | No change or fitting outside the parcel that affects the building’s appearance without written approval. | Grilles, awnings and balcony glass usually follow an approved design. |
One approval never replaces the other. My renovation permit guide for JB covers the council side.
Which works need what approval?
No national list exists, so this combines the by-laws with what I see on JB renovation forms.
| Type of work | Management approval | Council or other authority |
|---|---|---|
| Painting, loose furniture, light fittings | Often just a notice; check the house rules | Not usually |
| Flooring, kitchen cabinets, wardrobes, false ceilings | Yes; some buildings have floor-covering rules | Not usually, unless wiring or plumbing moves |
| Hacking non-structural walls, re-tiling bathrooms | Yes, with drawings and the waterproofing method | Possibly, if layout or services change; ask |
| Moving plumbing, full rewiring, moving external doors or windows, adding a platform | Yes | Yes (by-law 28) |
| Grilles, balcony enclosure, awnings, aircon outdoor units | Yes, usually to an approved design (by-law 29) | Depends on the work; ask |
| Joining two units | Yes | Yes, plus strata title questions (see combining two condo units) |
How the application works, step by step
- Get the paperwork. The renovation form, house rules, deposit amount and any approved designs for grilles or aircon brackets.
- Prepare the scope and drawings. What changes, materials and, for wet areas, the waterproofing method. Some buildings want an engineer’s sign-off for certain works (SAYS, May 2026).
- Give contractor details. Including its CIDB registration: section 25 of the CIDB Act 1994 requires it, and CIDB said in March 2024 that unregistered contractors face fines of RM10,000 to RM100,000. Check on CIDB’s online contractor search.
- Pay the deposit and sign the undertaking. Many forms include an indemnity for damage to common property.
- Get council approval for by-law 28 items before work starts.
- Collect the approval letter and workers’ passes, and tell the units beside and below your dates and hours.
- Finish, inspect and claim the deposit after a joint inspection with a written result.
Start only once approval is in writing. See also hiring an interior designer or contractor and renovation costs in JB.
The renovation deposit: amount, deductions and refund
By-law 27 allows a deposit but sets no amount; SAYS (May 2026) described RM2,000 to RM5,000 or more as typical. I found no national rule on the amount or refund deadline, so your building’s rules decide.
| Question | What usually happens | What to do |
|---|---|---|
| What is it for? | Damage to lifts and common property, uncleared debris, rule breaches | Check the form lists the deductible items |
| When is it refunded? | After the work ends and the common areas are inspected | Get the refund timeline in writing before paying |
| Who pays it? | Normally the owner, who answers to the management | Agree with your contractor who bears deductions its workers cause |
| What if money is deducted? | The management should say what was damaged and the repair cost | Ask for photos and an itemised statement |
My advice to clients: take dated photos of the lift, corridor and lobby on the first and last days. A dispute over a scratched lift panel then becomes a simple comparison.
Planning to buy and renovate a JB condo?
Tell me the building. Before you commit, I’ll ask the management office for its renovation form, deposit, working hours and any design rules for grilles or balconies.
WhatsApp JasonWorking hours, noise, lifts and debris
Hours and noise
Each building sets its own hours. SAYS described the usual pattern: hacking and drilling only in approved weekday hours, with Sundays and public holidays often excluded. Check your building’s by-laws and house rules for night-time quiet hours. If you live next to a renovation, see noisy neighbours in a condo.
Lifts and common areas
Expect to book the service lift, line it with protective panels and keep corridors clear. Materials blocking a fire escape or propping open a fire door are a safety issue, not just a house-rule breach (see fire safety and lifts in condos).
Debris
Debris normally has to be bagged and taken out of the building by the contractor, not left in the refuse chamber or chute. Ask where it goes: illegal dumping is enforced in Johor under the Solid Waste and Public Cleansing Management Act 2007 (Act 672), and Bernama reported 18 cases of illegal waste disposal prosecuted in Johor by early September 2025. My guide to bulky waste and renovation debris disposal in JB covers the options.
Wet areas and the unit below
Hacking bathroom or kitchen floor tiles can break the waterproofing layer, and the unit below finds out first. Under section 142 of the Strata Management Act 2013, a ceiling leak is presumed to come from the unit or common property above unless shown otherwise, and under Part XV of the 2015 Regulations the management must inspect within 7 days of a written complaint and then issue a certificate (Form 28) naming who repairs.
Write the waterproofing method into the contract, ask for a water (ponding) test before tiling with photos, and keep the contractor’s warranty in writing.
If you are on the receiving end, see water leaking from the unit above. For kitchens, see wet vs dry kitchens.
New condos: inspect before you renovate
If you bought from a developer, the statutory sale and purchase agreement gives a defect liability period of 24 months from vacant possession, and the developer must repair defects reported in writing within 30 days. Hacking or covering a defect before reporting it makes the claim harder to prove, so inspect, report and let the developer repair first, then renovate. See my vacant possession defect checklist and latent defects after the DLP.
What happens if you renovate without approval
| From whom | Possible consequence |
|---|---|
| Management (JMB or MC) | Stop-work instruction, deposit deductions, fines of up to RM200 per breach under an additional by-law, and restoring the facade or common property at your cost |
| Strata Management Tribunal or court | The management or a neighbour can seek to enforce a by-law, stop a breach and claim damages |
| Council | For works needing its approval, fines under section 70 of the Street, Drainage and Building Act 1974 (up to RM50,000 plus up to RM1,000 a day) and stop or demolition orders under section 72 |
Councils in Johor do act on this. MBIP told The Star in September 2026 that it had found 57 cases of unauthorised structural modifications since 2022, mostly buildings converted into high-density rentals. For how approved and unapproved work affects a sale, see renovations and resale value in JB.
Tenants, landlords and owners abroad
- Tenants need the owner’s written consent, and most offices want the owner to sign the form (see who pays for repairs).
- Landlords stay answerable for a tenant’s works, so ban alterations without written consent in the tenancy agreement.
- Owners abroad can sign by email where the management accepts it, appoint someone for the final inspection, or use a power of attorney (see managing JB property from overseas). Tell your insurer about major works (see home insurance in JB).
Disputes over approvals or the deposit
- Write to the management, asking which by-law or house rule applies and for the inspection report or itemised deductions.
- Raise an unfair rule at a general meeting; additional by-laws change by special resolution (see condo AGM voting).
- Complain to the Commissioner of Buildings (Pesuruhjaya Bangunan, COB) at your council, such as MBJB or MBIP.
- File at the Strata Management Tribunal, which hears Fourth Schedule claims up to RM250,000, including by-law disputes, for a RM100 residential fee through KPKT’s e-TPS. Check that your claim fits (see the Strata Management Tribunal in Johor).
A dispute with your contractor is different: home-renovation claims of up to RM50,000 go to the Tribunal for Consumer Claims (TTPM) for a RM5 fee. See renovation contractor disputes.
Buying a condo to renovate, or one already renovated
Get the building’s renovation rules before you sign. For a renovated unit, ask for the approval letters, especially for enclosed balconies, moved windows or relocated bathrooms, and ask the management about past leak complaints. See checking condo management before buying and buying an older condo.
Where to buy if this matters to you
- JB Sentral and Bukit Chagar: high-rise units near the CIQ and the RTS Link station.
- Mount Austin: condos and serviced residences popular with families.
- Tebrau, Setia Indah and Molek: older condos where buyers often redo kitchens and bathrooms.
- Iskandar Puteri: newer condos where defect checks come before renovation.
- Danga Bay and Permas Jaya and Senibong: waterfront and east-side condos.
Compare them on my JB property map, or browse new launches in Johor Bahru.
More Johor living guides: Renovation permits in JB · Condo by-laws, access cards and visitors · Maintenance fees and sinking fund · Soundproofing a condo unit
Frequently asked questions
Do I need management approval to renovate my condo in Malaysia?
Yes. By-law 27 of the standard strata by-laws (Third Schedule, Strata Management (Maintenance and Management) Regulations 2015) bars renovating without the management’s prior written approval, plus the authority’s where required.
How much is the renovation deposit for a condo in Johor Bahru?
No national amount is fixed. The by-laws allow a deposit, and a May 2026 SAYS guide put the usual range at RM2,000 to RM5,000 or more. Your building’s house rules set the figure.
When do I get my renovation deposit back?
Usually after the work ends and the management inspects the common areas. No national rule sets a deadline, so get the refund timeline and possible deductions in writing before you pay.
Which condo renovations also need council approval?
Under by-law 28: adding a platform, moving an external door or window, changing a safety feature, moving plumbing or sewerage and rewiring the whole unit. In JB the council is MBJB, MBIP, MBPG or MPKu.
Can a tenant renovate a rented condo unit?
Only with the owner’s written consent, and most management offices want the owner to sign the form. The owner stays answerable to the management for damage and breaches.
What can I do if the management keeps my renovation deposit?
Ask in writing for the by-law relied on and an itemised list of deductions. Then complain to the Commissioner of Buildings at your council, or file at the Strata Management Tribunal (up to RM250,000; RM100 residential fee).
Renovating or buying a condo in JB?
Tell me the building and what you want to change. I will get the management’s renovation form, deposit, hours and design rules, and for a renovated unit, ask the seller for the approval letters before you offer. You can also book an appointment for a viewing, or a Zoom consultation if you are abroad.
Sources: Strata Management (Maintenance and Management) Regulations 2015, P.U.(A) 107/2015, Part XV and Third Schedule by-laws 27 to 29 (copy published by DBKL), in force June 2015, checked November 2026; Strata Management Act 2013 (Act 757), sections 32, 70 and 142 (copy published by DBKL), checked November 2026; Attorney General’s Chambers, Laws of Malaysia online, checked November 2026; Malay Mail, “Buying a strata home: the rules that can govern your pets, parking and even your access card”, 29 September 2026; SAYS, “Here’s what you can and cannot do when renovating your condo in Malaysia”, 12 May 2026; Street, Drainage and Building Act 1974, Part V, sections 70 and 72 (as published by the National House Buyers Association), checked November 2026; The Star, “MBIP cracks down on illegal hostels”, 26 September 2026; CIDB, reminder to register and renew contractor registration (Act 520, section 25), 20 March 2024; CIDB, contractor search, checked November 2026; Bernama, “18 cases of illegal waste disposal prosecuted in Johor as of September”, 6 September 2025; The Sunday Star, on the 24-month defect liability period (reproduced by the National House Buyers Association), 16 December 2007; KPKT, Soalan Lazim Tribunal Pengurusan Strata, updated 9 July 2025; KPKT, Strata Management (Strata Management Tribunal) Regulations 2015, P.U.(A) 103, 1 June 2015; KPKT, e-TPS portal, checked November 2026; KPDN, Tribunal for Consumer Claims Malaysia, Frequently Asked Questions, updated 30 August 2024
Jason Lim, REN 84424, IQI Realty Sdn. Bhd. E (1) 1584/6. General information checked on 15 November 2026, not legal advice. By-laws, house rules and deposits differ between buildings and change over time; confirm with your management office, the Commissioner of Buildings at your council (MBJB, MBIP, MBPG or MPKu) and a lawyer before you renovate or start a claim.