Real Property Development Bill Malaysia: Status, Option to Purchase and What Buyers Should Know

中文 · Bahasa Melayu · Bahasa Indonesia

By Jason Lim, REN 84424 · IQI Realty · Checked on 14 November 2026

The Real Property Development Bill is a proposed law that would replace the Housing Development (Control and Licensing) Act 1966 (Act 118) and bring commercial projects, not just housing, under the housing ministry’s licensing rules. It is not law yet. It was due to be tabled in June 2026, but the latest ministry statements I could find, from July and August 2026, said it was still in the final stage of drafting, and I found no report of it being tabled as of 14 November 2026. Until it passes, Act 118 and your sale and purchase agreement (SPA) decide your rights.

Quick answer

  • Not law: the June 2026 tabling target passed. On 31 July and 10 August 2026 the housing minister said the draft was at its final drafting or review stage. No tabling date had been announced in the reports I found.
  • What it would do: fully replace Act 118 and extend developer licensing and buyer protection to commercial developments such as shop lots and mixed projects.
  • Option to Purchase (OTP): a proposed window before the SPA in which the buyer or developer can walk away. The minister’s example in August 2026 was six months. In October 2026 KPKT said buyers could pay up to 5% of the price at this stage; if the developer does not go ahead, buyers get a full refund plus interest. A buyer who exits may face charges. The details are still under study.
  • Other proposals: higher penalties, stronger rules on payment collection and quality, and clearer audit powers (November 2025).
  • Today’s protection: housing projects use the statutory Schedule G or H SPA, with 24 or 36 months to hand over, late-delivery damages of 10% a year and a 24-month defect period.

What the Real Property Development Bill is

Since 1966, Act 118 has governed how licensed developers in Peninsular Malaysia sell homes before they are built: licences, advertising permits, the Housing Development Account that holds buyers’ money, and the statutory SPA forms. It covers housing only, so buyers of shop lots, offices and some mixed developments have no statutory SPA and, the minister has said, no recourse under the Act when a project fails.

The Real Property Development Bill (also reported as the Property Development Act) is the ministry’s answer. Based on ministry statements, it would:

  • Replace Act 118 in full, rather than amend it (Bernama, 20 November 2025).
  • Cover commercial projects such as shop lots and other commercial developments (Bernama, 10 August 2026). In May 2025 the ministry included mixed developments with SoFo and SoVo units, which count as commercial even though people live in them.
  • Apply to Peninsular Malaysia, like Act 118. The minister said so in May 2024. Sabah and Sarawak have their own housing laws.

Where the bill stands in November 2026

The tabling date has slipped more than once:

DateWhat was said or done
14 May 2024The minister said a new law for Peninsular Malaysia was being considered, with tabling expected in 2025.
17 May 2025The ministry said the new law would cover certain commercial developments and introduce an Option to Purchase framework.
20 November 2025The minister said the bill would be tabled in June 2026 and would fully replace Act 118.
7–8 May 2026The ministry said it was studying an Option to Purchase clause under the proposed bill.
31 July 2026The minister said the draft was at the final stage of drafting. No tabling date was given.
10 August 2026At the launch of the National Housing Policy 2026–2035, the ministry listed a new Property Development Act among four housing laws to be made or amended, at the final review stage.
15 October 2026KPKT said the Option to Purchase was still under study: buyers could pay up to 5% of the price before the SPA, with a full refund plus interest if the developer does not go ahead. The statement did not mention a tabling date for the bill.
Sources: Malay Mail, 14 May 2024; The Edge Malaysia, 17 May 2025; The Star, 20 November 2025; Bernama, 20 November 2025, 8 May 2026, 31 July 2026 and 10 August 2026; KPKT press release, 8 May 2026; The Star, 15 October 2026.

The current Dewan Rakyat meeting runs until 8 December 2026 (Bernama, 14 October 2026). Once tabled, a bill must pass both houses, receive royal assent and be gazetted before a commencement date is set. Check Parliament’s bills list or KPKT for the latest.

What the bill is expected to change

No draft text has been published, so treat the right-hand column as proposals only.

AreaAct 118 todayProposed under the new bill
What is coveredHousing developments in Peninsular MalaysiaHousing plus commercial projects such as shop lots and mixed developments
Sale contractStatutory Schedule G (landed) or Schedule H (strata) SPA for licensed housing developersNot yet published. The ministry has spoken of stronger rules on payment collection, quality and maintenance
Before the SPANo statutory option stage. Regulation 11(2) bars collecting payments the contract does not prescribeAn Option to Purchase stage in which either side may withdraw
Troubled projectsMinistry task force, blacklisting of developers in housing projectsClearer technical audit and investigation powers to detect problems earlier, with commercial projects covered
DisputesTribunal for Homebuyer Claims, up to RM50,000 per claimNot announced
Sources: Housing Development (Control and Licensing) (Amendment) Regulations 2015, P.U.(A) 106/2015; KPKT, Tribunal for Homebuyer Claims FAQ, checked November 2026; Bernama and The Star, 20 November 2025; Bernama, 10 August 2026. Proposals may change.

The bill sits alongside other reforms: the electronic SPA (eSPA), the Housing Integrated Management System (HIMS) that tracks project money, the TEDUH platform and audits of Housing Development Accounts. These do not depend on the bill.

The Option to Purchase clause, as proposed

The Option to Purchase (OTP) is the part buyers ask me about most. It has not been finalised, and descriptions have shifted.

How it would work

  • An exit before the SPA. In May 2025 the ministry spoke of letting buyers end their SPA if unhappy with progress. By May 2026 it described a stage before the SPA is signed in which both the buyer and the developer can withdraw.
  • A set period. On 10 August 2026 the minister gave six months as an example of the window. The actual period would be in the law or the agreed terms.
  • Developer exit. If the developer judges that the project will not work, for example because sales are weak, it can withdraw in that period. Under the October 2026 proposal, buyers would then get a full refund, plus interest, of the up to 5% of the price paid at the option stage.
  • Buyer exit. Buyers can withdraw too, for example after finding a more suitable home, but subject to charges and the agreed terms. A later Malay Mail explainer mentioned administrative charges or interest.
  • Timing. In August 2026 the minister said the OTP was expected by the end of 2026. On 15 October 2026 KPKT said it was still being studied and gave no start date (The Star, 15 October 2026).

The aim is prevention: developers test real demand before construction is far along, so fewer projects stall. Its task force had resolved 1,647 sick or abandoned private projects over three years, and the target is no abandoned housing projects by 2030 (Malay Mail, 10 August 2026). Singaporeans know the term from home purchases there, but don’t assume Malaysia’s version will use the same fees or periods.

What supporters and critics say

  • Developers. REHDA backed the clause in principle in May 2026 but said it must be clear, practical and fair to both sides.
  • Consumer groups. The Consumer Association of Penang wants option fees held in regulated escrow or stakeholder accounts, a time limit on options, conditions developers must meet first (land, approvals, financing) and full refunds with compensation for unjustified cancellations.
  • Doubts about the fix. A June 2026 opinion piece in The Star argued an OTP alone does not fix the financing weaknesses behind abandoned projects, and build-then-sell would go further. See my guide to build-then-sell vs sell-then-build.

How it compares with today’s booking fee

Most new launches start with a booking form and fee. Under the statutory SPA the first payment is the 10% on signing, and Regulation 11(2) of the 1989 Regulations bars collecting payments the contract does not prescribe. Even so, booking fees are widely taken, and refunds can be hard to get. The same June 2026 article recalled a National House Buyers Association proposal: cap the fee at RM5,000 or 1% of the price, whichever is lower, ring-fence it and refund it within 14 days. An OTP in law could put this stage on a clear footing. Until then, my guide to backing out of a purchase covers what happens if you change your mind.

Looking at a new launch in JB?

Send me the project name. I’ll tell you whether it is sold under the statutory Schedule G or H SPA or a commercial contract, what the booking terms say, and what to check on TEDUH before you pay anything.

WhatsApp Jason

What it could mean in Johor Bahru

The commercial side of the bill matters in JB. Serviced apartments, SOHOs and SoFos on commercial land are a familiar product around the city centre near the RTS Link station and in parts of Iskandar Puteri, and new townships include rows of shop offices. A commercial-titled unit is usually sold on the developer’s own SPA, not Schedule G or H, so the delivery deadline, late-delivery damages and defect period depend on that contract. My guide to serviced apartments on commercial title explains the running-cost side, and condo vs landed vs SOHO compares the product types.

Foreign buyers: the bill would not change Johor’s own rules. State consent, the RM1 million minimum (with only limited exceptions, for example some serviced apartments sold by developers with state approval; no area is exempt as a whole) and the approval fee are set by the state under the National Land Code. See my guide to Johor’s foreigner minimum price and quota.

What protects you today

These checks work now:

  1. Check the developer on TEDUH. teduh.kpkt.gov.my shows the developer’s licence and advertising permit, project progress, and whether a project is delayed, troubled or abandoned (Malay Mail, 7 September 2026). See checking a developer before you buy.
  2. Ask which SPA you will sign. Schedule G or H fixes 10% on signing, eight construction stages, handover within 24 months (landed) or 36 months (strata), damages of 10% a year if late and a 24-month defect liability period. See the SPA explained and the progressive payment schedule.
  3. If it is a commercial SPA, read the key terms. Check the delivery period, late-delivery damages, defect period, payment stages and termination rights with your own lawyer.
  4. Pay into the right account. Housing purchase money goes to the project’s Housing Development Account (Act 118, section 7A). Never pay cash or into a personal account; keep receipts.
  5. Know where to claim. The Tribunal for Homebuyer Claims hears SPA claims up to RM50,000 each for a RM10 fee (KPKT). See also late vacant possession and LAD claims and what to do if a project is abandoned.

Should you wait for the new law before buying?

My honest view: don’t plan a purchase around the bill’s timing. The tabling date has moved before, the text is not public, and any transitional rules are unknown, so you can’t count on a new law covering an SPA you sign now. Housing projects already come with a statutory SPA. For a commercial-titled unit, the bill is a reason to read the contract carefully, not to avoid the product. Completed projects also remove construction risk; see subsale vs new launch in JB and the CCC explained.

My guides to the National Housing Policy 2026–2035, the Residential Tenancy Act and the Urban Renewal Act cover the other housing reforms.

Where to buy if this matters to you

Compare areas on my JB property map, or use the sales gallery checklist before your next visit.

More Johor living guides: The SPA explained · Abandoned housing projects · The Homebuyer Claims Tribunal · Checking a developer · Build-then-sell vs sell-then-build

Frequently asked questions

Has the Real Property Development Bill been passed in Malaysia?

No. It was due to be tabled in June 2026, but on 31 July and 10 August 2026 the housing minister said the draft was still at its final drafting or review stage. I found no report of it being tabled as of 14 November 2026, so Act 118 still applies.

What is the Option to Purchase in the Real Property Development Bill?

A proposed stage before the SPA in which the buyer or the developer can withdraw. The minister gave six months as an example. In October 2026 KPKT said buyers could pay up to 5% of the price at this stage, with a full refund plus interest if the developer does not go ahead; a buyer who withdraws may face charges. Details are still under study.

Will the new law cover serviced apartments, SOHOs and shop offices?

That is the aim. The ministry says the bill will extend regulation to commercial projects such as shop lots and mixed developments, including SoFo and SoVo units on commercial land. The exact scope will depend on the final text.

Does the Real Property Development Bill replace Act 118?

Yes, as proposed. In November 2025 the minister said it would fully replace the Housing Development (Control and Licensing) Act 1966. Until it is passed and in force, Act 118 and its statutory Schedule G and H SPAs continue to apply.

Should I wait for the new law before buying a new launch in Johor Bahru?

I wouldn’t plan around it. The timing is uncertain and the text is not public. Housing projects already use the statutory SPA; for commercial-titled units, read the contract terms with your lawyer and check the developer on TEDUH.

Can I walk away from a booking before signing the SPA today?

There is no statutory option stage yet. Regulation 11(2) bars collecting payments the contract does not prescribe, but booking fees are widely taken and refunds depend on the developer. Get the refund terms in writing and pay only to the developer’s company account.

Buying a new launch or commercial unit in JB?

Tell me the project and your budget. I will check the developer’s record, the SPA type and recent transaction ranges nearby, and explain your rights under today’s law. You can also book an appointment, or a Zoom consultation if you live overseas.

Sources: Malay Mail, “Govt mulling Real Property Development Act for Peninsular Malaysia”, 14 May 2024; The Edge Malaysia, “Govt considers new law to protect mixed, commercial property buyers”, 17 May 2025; Bernama, “KPKT to table Real Property Development Bill in June 2026”, 20 November 2025; The Star, on the Real Property Development Bill and five housing reforms, 20 November 2025; KPKT press release on the Option to Purchase mechanism, 8 May 2026; Bernama, “KPKT to introduce OTP mechanism, allowing pre-SPA withdrawal flexibility”, 8 May 2026; The Star, “Rehda: Proposed clause offers greater flexibility”, 14 May 2026; The Star, “Groups want proper controls of Option to Purchase mechanism”, 14 May 2026; The Star, “Nga: Proposed OTP to protect homebuyers”, 15 October 2026; The Star, “Time to legalise booking fees?” (opinion), 7 June 2026; Bernama, “Draft Real Property Development Act in final stage, says Nga”, 31 July 2026; Bernama, “KPKT to draft, amend four housing laws under National Housing Policy 2026-2035”, 10 August 2026; FMT, “4 akta bakal digubal, dipinda bawah Dasar Perumahan Negara 2026-2035”, 10 August 2026; Malay Mail, “Prevention is better than cure”: govt unveils OTP exit clause, 10 August 2026; Malay Mail, “National Housing Policy: what does the policy mean for Malaysians?”, 24 August 2026; Malay Mail (Bernama), KPKT urges buyers to check TEDUH, 7 September 2026; Bernama, Parliament’s focus this week (sitting dates to 8 December 2026), 14 October 2026; Housing Development (Control and Licensing) (Amendment) Regulations 2015, P.U.(A) 106/2015, in force 1 July 2015; KPKT, Soalan Lazim Tribunal Tuntutan Pembeli Rumah (RM50,000 limit, RM10 fee), updated January 2023, checked November 2026; Housing Development (Control and Licensing) Act 1966 (Act 118), section 7A (Housing Development Account), and Housing Development (Control and Licensing) Regulations 1989, regulation 11(2)

Jason Lim, REN 84424, IQI Realty Sdn. Bhd. E (1) 1584/6. General information checked on 14 November 2026, not legal advice. The bill is a proposal and may change; check with Parliament and KPKT, and have a lawyer review any booking form or SPA.